After the Demolition

Once the demolition is completed, you must remove all rubbish and building materials from the property as well as fill and level the excavation to an elevation compatible with abutting properties. You should also seed the site with coarse grass.

If required, you must get approval from Public Works to remove driveway crossings that are no longer required or to remove any structures that encroach onto the property.

For properties located in the downtown zone, commercial zone or Transitional Area Residential zone (bounded by College Avenue, Albert Street, 13th Avenue and Broad Street), you must provide a perimeter screen fence or landscaping that complies with the regulations contained in Regina Zoning Bylaw No. 9250.