Wastewater Treatment Plant Project

Project Highlights

June 2014 - Excavation begins (Early Works)
July 2014 - Project agreement signed
August 2014 - EPCOR begins plant operations
August 2014 - Greenfield site excavations complete
October 2014 - Two tower cranes erected
November 2014 - Bioreactor base slabs complete
March 2015 - Grit Removal Tanks construction begins
June 2015 - Secondary Clarifiers construction begins
November 2015 - Grit Removal Tanks construction complete

March 2016 - UV system in service
April 2016 - New BNR & Secondary Clarifiers begin operations
August 2016 - Secondary Clarifiers construction complete
September 2016 - Digested Sludge Tank erected
October 2016 - Biogas System in service
December 2016 - Substantial completion

Construction Statistics

145 - Peak trade workforce reached in April 2015
685,000 - Total construction hours
3000 - Safety meetings
0 - Lost time injuries during the 30-month construction period
12,000 - Metres of cable installed for the main electrical system
275,000 - Cubic metres of soil excavated
1,775,000 - Kilograms of reinforced steel bar installed at the plant
8,000 - Metres of electrical conduit installed at the plant

Residents should contact Service Regina at 306-777-7000 for billing inquiries, sewage backup, flooding or drainage concerns, water service or water quality issues.

EPCOR is building and will operate the plant as part of this contract. EPCOR should be contacted for any concerns related to construction and operation of the facility by calling 1-844-412-3458 (toll free). 