PL202500394-8101 Dewdney Avenue
Public Notice - 8101 Dewdney Avenue
North Central Drainage Project
rth Storm Channel. Newly-installed reinforced concrete pipe storm main. Drilling of a Steel
Casing/Carrier Pipe Under CN Rail 2/6 Concrete pipe is on-site ready
to be installed further south along Athol Street and further north through Pony Park to connect to
the North Storm Channel. Fall 2020 Progress 6/6 This carrier pipe will house the 200mm PVC
wastewater pipe. This work is part of some re-routing work that is needed to take place to allow
installation of the large diameter (1600mm) storm pipe. Fall 2020 Progress 3/6 Drilling of a Steel
Casing/Carrier Pipe Under CN Rail 4/6 This carrier pipe will house the 200mm PVC wastewater pipe.
This work is part of some re-routing work that is needed to take place to allow installation of the
large diameter (1600mm) storm pipe. This is the 1.5 meter diameter steel pipe that will be
installed under CN Rail. This pipe will support and will contain the plastic (PVC) pipe that
actually is used to transport storm water. North Central Drainage Project Drilling of a Steel
Casing/Carrier Pipe Under CN Rail 1/6 To reduce the risk of surface and basement flooding, the
North Central Drainage Project will replace and upgrade the storm sewer system along both 2nd
Avenue and Athol Street. Installed storm main west along 2nd Ave as well as the reconnected
domestic main in the intersection of 2nd Ave and Argyle St. ...
New Commercial, Industrial, Institutional, Mixed Use Buildings and Additions
port NECB Tiered Performance Report Energy Efficiency Compliance Options Helpful Information:
Advisory Documents Commercial Information PackageSite Plan Landscape
Plan Barrier-Free Design Guide Submit your application through our new online eBuild software or
in-person at City Hall. The City will review your application to ensure it meets all building,
heritage, zoning, landscaping, engineering, environmental, disposal, assessment, open space and
utility regulations and/or bylaws. Apply Online If applicable, contact Technical Safety Authority
of Saskatchewan (TSASK) for inspections and permits for gas or electrical work. PLEASE NOTE:
Building permit application forms must be filled out in full; incomplete applications will not be
accepted. Legal land owner information must match what’s listed on land title. The individual
signing for the legal land owner must be on title or must be authorized to sign on the legal land
owner’s behalf via an authorization letter from the legal land owner. If a company is listed on
title as the legal land owner, the individual signing on behalf of the owner must print their name
and position associated with the company and must have signing authority. If someone is designated
to sign on behalf of the owner, this authorization can be provided via an authorization letter from
the legal land owner (individual giving authority must list name, position, and have signing
authority). ...
Irrigation Systems
View the Standard Construction Specification for Irrigation Systems.
2020 Official Summary Results
View the 2020 Election Official Results.
Application for Facility Rental
To book a recreation centre or outdoor pool, use our application for facility rental form.
PL202500394-8101 Dewdney Avenue (2)
Public Notice - 8101 Dewdney Avenue
City Centre Incentive Program
e? Prospective applicants can reach out to our team for a pre-application meeting. A
pre-application request must include: Address of the proposed site.
A description of the proposal being contemplated. Attachment of any available renderings/plans.
Projected start and end date. Click on the Request a Meeting button below and fill in the email
prompts with details of the proposed project. Once you have requested a meeting, our team will
review your documentation and arrange a meeting. Based on questions submitted, the City will ensure
the appropriate staff are available to attend the meeting. Request a Meeting What if there is no
remaining grant funding by the time I apply? The three-month intake period for applications allows
us to review applications for completeness and general eligibility under the program. Evaluation of
final eligibility and allocation of funding will take place once the application intake period is
closed. Frequently Asked Questions Heritage Properties & Conservation Community Investment
Grants Housing Office to Residential Conversion
Public Notice - 4801 Optimist Drive
Public Notice - 4801 Optimist Drive